Guide · Quotes
Reading and comparing Denver ADU quotes (2026)
LAST VERIFIED: SEPTEMBER 2026 · SOURCES: DENVER CPD FEE SCHEDULES, DENVER WATER, PUBLISHED DENVER BUILDER PRICING
Itemize every quote to these lines before comparing
| Line | What to confirm | Commonly missing |
|---|---|---|
| 1. Design and engineering | Architectural plans, structural engineering, survey | Survey; landmark-review drawings |
| 2. Permits and city fees | Building permit, plan review, zoning | Often listed as "by owner" |
| 3. Denver Water SDC + tap fees | System Development Charge (July 2026: $2,170 inside Denver) plus tap and meter | The single most-missed line |
| 4. Utility service | Electrical service or sub-panel, gas if any, sewer and water lines to the unit | Trenching distance; Xcel coordination |
| 5. Site work and foundation | Excavation, soil report, foundation type | Soil allowance; expansive-soil mitigation |
| 6. Shell | Framing, roof, windows, exterior | Fire-rated assemblies near property lines |
| 7. Mechanical, electrical, plumbing | Heating/cooling system type, fixtures count | Heat pump vs. gas; ERV |
| 8. Interior finish | Kitchen, bath, flooring, finish level with allowances stated | Allowance amounts left blank |
| 9. Site restoration | Landscaping, fencing, driveway or alley repair | Almost always excluded |
| 10. Contingency | Stated percentage, who controls it | Zero contingency is a warning, not a bargain |
| 11. Exclusions | An explicit list of what the price does not cover | If there's no exclusions section, everything not listed is excluded |
Why one quote is $160K and another is $280K for the "same" ADU
Run the two quotes through the eleven lines and the gap usually resolves into four causes: scope (lines 2, 3, 4, and 9 are missing from the lower one), method (a modular unit price vs. a site-built project price; see prefab vs. site-built), risk (one builder priced a soil allowance and a contingency, the other will invoice them as change orders), and finish (allowances of $40 vs. $120 per square foot for tile look identical on a summary page). Whatever's left after those four is the actual price difference, and it's usually far smaller than the headline suggested.
Two practical rules: ask each builder to re-submit on your eleven-line template (a serious builder will; the template protects them too), and never let a quote expire in under a week. See the full cost ranges in what an ADU really costs and how to check the builder behind the number in verify a contractor.