Guide · Permits & zoning

Denver ADU permits in 2026: the complete rules

LAST VERIFIED: AUGUST 2026 · PRIMARY SOURCES: DENVER CPD, DENVER ZONING CODE, COLORADO HB 24-1152 (C.R.S. 29-35-401–405)

Direct answer: Denver allows one ADU on any lot where a single-family home is allowed — no minimum lot size, no added parking requirement, and administrative (no-hearing) review. Detached units are capped by lot size (650 / 864 / 1,000 sq ft), limited to 24 ft and 1.5 stories, and must sit in the rear 35% of the lot. You'll need a zoning permit, a building permit, and a sewer-use and drainage permit (SUDP). Plan review runs about 4–8 weeks.
§1 — ELIGIBILITY

Can I build an ADU on my lot?

Almost certainly yes. Two changes opened the city up: Denver's citywide zoning amendment allowing ADUs in all residential zone districts, and Colorado's HB 24-1152 (compliance required by mid-2025), which requires every sizable Colorado municipality to allow at least one ADU per single-family lot by right, with administrative approval, no minimum lot size games, and limits on parking mandates. HOAs in Colorado can no longer ban ADUs outright.

Verify your specific situation in ten minutes: find your zone district on the Denver zoning map (maps.denvergov.org), then check the detached accessory building standards for that district. Two overlays that add steps: historic districts (Wash Park edges, parts of Capitol Hill, Country Club and others) require landmark review, which adds roughly 2–4 months and design-matching requirements; and HOA covenants, which can still regulate appearance and materials even where they can't prohibit the unit.

§2 — DIMENSIONAL STANDARDS

Size, height, and placement limits

DETACHED ADU — DIMENSIONAL STANDARDS, DENVER 2026
StandardRule
Max size, lot < 6,000 sq ft650 sq ft
Max size, lot 6,000–7,000 sq ft864 sq ft
Max size, lot > 7,000 sq ft1,000 sq ft
Max height / stories24 ft / 1.5 stories
PlacementRear 35% of the zone lot depth
Rear setback (one-story)5 ft typical; varies by zone and alley access
ParkingNone required for the ADU (per HB 24-1152)
Lot coverage / bulk planeZone-specific caps apply; ADU counts toward totals

Two rules trip up more projects than any others. First, bulk-plane geometry — Denver constrains the building envelope with an angled plane from the property line, which shapes what a 1.5-story unit can look like near a neighbor. Second, garage conversions that remove existing required parking for the main house can trigger a compensation requirement. Both are solvable at design stage and expensive to discover at review stage.

§3 — THE THREE PERMITS

What permits does a Denver ADU need?

  1. Zoning permit — confirms size, height, and placement comply with your zone district's standards.
  2. Building permit (residential construction) — full plan review of structure, life safety, energy code. Requires architectural drawings, site plan, and structural sheets.
  3. SUDP (Sewer Use and Drainage Permit) — Denver-specific and easy to miss in budgets: covers the ADU's wastewater and stormwater connections. Denver Water separately charges a System Development Charge for the new unit (see the cost guide for current figures).

Applications go through Denver CPD's online e-permits portal. Under HB 24-1152 the review is ministerial — administrative sign-off against written standards, no discretionary design review, no neighborhood hearing for a compliant application.

§4 — TIMELINE

How long does it take?

TYPICAL DENVER ADU TIMELINE, 2026
StageDuration
Feasibility + design + engineering1–3 months
CPD plan review (standard ADU)4–8 weeks
Historic district landmark review (if applicable)+2–4 months
Construction4–10 months
Application to move-in, all-in≈ 7–14 months

The single biggest controllable factor is submission quality: incomplete or non-compliant plan sets trigger resubmittal cycles that add weeks each round. This is the strongest practical argument for using a builder or designer who has already permitted ADUs in Denver specifically — see how to vet one.

§5 — RENTING IT OUT

Owner-occupancy and rental rules

Long-term rental (30+ days): no owner-occupancy requirement — Denver removed it in December 2024 (CB24-1303), so both the main house and the ADU can be rented to long-term tenants, and no rental license is required for the ADU itself.

Short-term rental (under 30 days): requires a Denver STR license (~$250/year), and the property must be the host's primary residence — pure-investment Airbnb ADUs are not permitted in Denver.

This guide summarizes rules as verified in August 2026 against Denver CPD publications, the Denver Zoning Code, and C.R.S. 29-35-401–405. Codes and fees change, and zone-specific standards vary; confirm your property's requirements with Denver Community Planning and Development before committing money. This is information, not legal advice.